Parapets are being completed in the third stage in the seventh section
RIEL Real Estate Corporation continues active construction in the Schengen RC.
In the third stage in the seventh section, we are reaching the final stage of parapets arrangement. Meanwhile, sections 9.1 and 9.2 are already being roofed, and the internal sanitation system has been laid.
In section 11, the floor waterproofing has been completed, and the second layer of screed in the basement is being poured. The builders have already covered the niches of engineering networks in public areas, and tiling in common areas is underway. At the same time, retaining walls are being installed.