Façade works are being completed in the fourth stage in B2-C1 and B2-C2 sections
June 24, 2024
RIEL Real Estate Corporation reports that the construction of the Shengen RC is actively underway. Currently, in the fourth stage, the façade arrangement is being completed in the sections. In B2-C3 sections, works on the allocation of electrical cables, pouring floor screed in the common facilities and plastering the walls are underway.
At the same time, in B1-C1 sections, the floor slab of the 11th floor has been completed, the external walls of the eighth floor are being masoned, and the installation of window structures is underway.