To the news list

In the house No. 6 of the second stage, facade work continues

November 20, 2023

REC RIEL reports that the construction of the second stage of Shengen RC is in progress. in the house No. 6 of the second stage, facade work continues.

In the house No. 5, the installation of sewerage in the basement is underway, the entrance groups are being arranged, and the apartment entrance doors are being installed.

In the houses No. 8 and 10, work began on installing railings.

Landscaping work is in progress.

You can find out more about the construction progress and the sales terms of purchasing apartments in Shengen RC in our sales department. Contacts are at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(032) 229-54-62
Feedback
The exchange rate as of 11/23/2024 is 41.37 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Shengen. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.