To the news list

In the house No. 5 of the second stage heat supply individual metres are set up

December 27, 2023

RIEL Real Estate Corporation reports that the construction of the second stage of Shengen RC is actively pursued. Now in the house No. 5 of the second stage, the builders are setting up heat supply individual metres, sewing up niches with plasterboard and puttying the walls, and preparing for pouring screeds in the basement.

In the house No. 6, the plastering of the walls has been completed, the façade work on the ground floor is at the final stage, and preparations are underway for the installation of screed in the basement.

In the houses No. 8 and 10, finishing work is being performed in the apartments and landscaping.

You can find out more about the construction progress and the conditions for selling apartments in Shengen RC in our sales department. Contacts are at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(032) 229-54-62
Feedback
The exchange rate as of 11/22/2024 is 41.37 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Shengen. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.