In the 10th section of the second stage, the floor slab of the 11th floor is cast

October 14, 2021

RIEL Real Estate Corporation reports that the construction of Shengen residential complex is actively pursued. In the 10th section of the second stage, the 11th floor slab is cast. This was announced by the construction project manager.

In the 8th section, the laying of the walls of the 11th floor is in progress; in the 5th section, the 9th floor is being built, and the laying of the 6th floor is completed in the 6th section.

It is reported that the installation of windows has begun at the object, and the insulation and decoration of facades in some sections is being performed.

You can choose a floor and layout, as well as find out other details about the terms for purchasing an apartment in Shengen RC in our sales departments. Our managers will be happy to advise you on any issue. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(032) 229-54-62
Feedback
The exchange rate as of 11/28/2024 is 41.6 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Shengen. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.