Construction work is continuing on the third phase of the Shengen residential development in Lviv.

In Building 7, monolithic construction of the platform lift for people with reduced mobility has been completed. Flooring and plastering works have also been completed in the basement premises. Installation of the individual heating substation (IHS) has now commenced.

In Building 9, flooring and plastering works in the basement premises have been completed. Installation of the IHS has begun, together with façade works to the basement level.

Landscaping works have also commenced throughout the development.

In addition, specialists from the Bureau of Technical Inventory (BTI) have started measuring apartments and non-residential premises across the buildings.

Shengen residential development in Lviv offers contemporary architecture, functional apartment layouts and carefully considered solutions designed to support comfortable everyday living.

Its convenient location close to the city’s major transport routes provides excellent connectivity to all parts of Lviv. The development’s on-site infrastructure will be further enhanced by a shopping centre offering a range of essential services just moments from home.

For further information about available apartment layouts, purchase options and current offers, please visit one of RIEL’s sales offices:

  • Kyiv: 17K Dniprovska Embankment or 5B Rostyslavska Street (Elyseum Residential Development, Ground Floor);
  • Lviv: 116 Bohdana Khmelnytskoho Street or Stryiska Street (2 Persenkivka).
We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.